Looking to Reset Process, Metro to Approve ‘No Build’ Alternative for Lower 710 Freeway Widening

710 Freeway ramps towering over nearby residences. Photo by Joe Linton/Streetsblog L.A.

LongBeachize_Ad_Concepts

This article supported by Los Angeles Bicycle Attorney as part of a general sponsorship package. All opinions in the article are that of the author, and do not necessarily reflect those of LABA. Click on the ad for more information.

In an acknowledgement that its 710 Freeway widening plan is not feasible, Metro now intends to approve a "no build" alternative, while the agency makes new plans for more equitable, multimodal 710 corridor projects.

For decades, Metro and Caltrans have pushed to widen the lower 710 Freeway. Early on Caltrans proposed to widening the 710 from 8 to 16 lanes - and early on community groups fought the agencies' plans because they would increase pollution in one of the most polluted corridors in the U.S., harming the health and well-being of predominantly low-income communities of color residing there. Metro and Caltrans pushed various versions of the widening, circulating draft widening plans (Environmental Impact Reports - EIRs) in 2012, 2013, and 2017. In 2018, the Metro board approved an EIR "locally preferred alternative" that would have cost $6-plus billion to tear down more than a hundred homes and businesses to widen the 710 by two more lanes.

Corridor communities, organized together as the Coalition for Environmental Health and Justice (CEHAJ), had long insisted on no displacement and unsurprisingly opposed Metro's approved alternative. In late 2020, the federal Environmental Protection Agency ruled that Metro's 710 widening alternative would violate clean air law. When the EPA decision was made public in May 2021, Caltrans soon paused the project, after which the Metro board suspended it, forming a (yet another) 710 Freeway task force to advise on what Metro is now calling a "multimodal investment strategy" for the corridor.

Metro's 710 task force met last night. Much of the meeting was dedicated to discussion of the task force's mission statement and goals (see pages 29-30 of Metro's presentation); there was also an update on how Metro and Caltrans plan to finalize the pending 2017 EIR.

Metro staff announced that next month the lower 710 Freeway EIR would come to the Metro for approval of the "no build" alternative.

Environmental studies always include a no build alternative as a sort of baseline to measure project impacts against - but it is pretty unusual for an agency to actually select the no build alternative. It's rare that agencies would spend millions of dollars studying the impacts of projects that they don't plan to build in some form or another. (Metro already spent more than $160 million on the current round of 710 Freeway studies and early projects.)

But why bother? Does the Metro board really need to approve not doing something?

Metro rationale for approving no build alternative for 710 Freeway widening - via Metro presentation
Metro rationale for approving no build alternative for 710 Freeway widening - via Metro presentation
Metro rationale for approving no build alternative for 710 Freeway widening - via Metro presentation
xxx
Metro's flow chart showing how the (red) clean air decision took out the (blue, green) freeway widening, and its implications for Early Action Program - via Metro presentation
xxx

Last night Metro and Caltrans staff couched the approval behind a lot of clichéd metaphors: close the door, close the chapter, close the book before opening a new book.

But their rationale seems to be more along the lines of getting back to building more freeway projects. Part of the 710 Freeway widening was its "early action program" (EAP), generally involving widening roads and ramps onto and off of the 710 Freeway. The Gateway Cities Council of Governments (GCCOG) had been greenlighting early steps toward many of these smaller widenings - but those EAP projects are languishing, waiting for blanket approval in the big 710 EIR.

Closing out the 710 EIR will allow for processes to get the smaller widening projects out of limbo.

xxxx
Approving the 710 Freeway no build alternative could allow smaller projects (EAP - early action program) to proceed through other environmental processes - via Metro presentation
xxxx

Metro staff stated that they are currently preparing the final no build EIR, anticipated to be approved by the board in May. After that the document would have 30-day public review process, then Caltrans would issue a record of decision.

Correction: This story initially erroneously stated that Metro had spent $160 million on 710 Freeway environmental studies, but the $160+million (shown in Metro's FY22-23 preliminary budget) that Metro already spent on the 710 widening project includes the project EIR studies as well as preliminary projects - mostly road-widening in preparation for the freeway widening.

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

Metro Committee Approves Revoking $435K Culver City Grant due to Bike Lane Removal

Culver City recently removed protected bike lanes funded by a Metro Active Transportation grant, now Metro wants its money back

November 20, 2024

Touring the Puente Hills Landfill Slated to Become the Future “Griffith Park of the San Gabriel Valley”

Puente Hills Landfill Park is expected to open in 2027, with 140 acres of trails and stunning vistas all the way to the ocean

November 19, 2024
See all posts