Metro Breaks Ground on Early Phase of Southeast Gateway Light Rail Construction

The initial $7 billion SE Gateway Line segment will extend 14.5 miles from Artesia to the South L.A. community of Florence, with connections to the Metro A and C Lines
2:43 PM PDT on October 31, 2024
Metro Breaks Ground on Early Phase of Southeast Gateway Light Rail Construction
Southeast Gateway Line ceremonial groundbreaking. Photos by Joe Linton/Streetsblog

“We are not just shovel-ready, we are putting those shovels in the ground!” County Supervisor and Metro Board Chair Janice Hahn proclaimed at yesterday’s groundbreaking celebration for Metro’s Southeast Gateway light rail line. The line, which will serve southeast L.A. County, is not yet fully funded, so the groundbreaking was for the key pre-construction phase of advance utility relocation.

The ceremony took place at the site of the city of Artesia’s future Pioneer Boulevard Station, now a vacant rail right-of-way.

County Supervisor and Metro Board Chair Janice Hahn speaking at yesterday’s groundbreaking

“Expansion of our Metro system… is finally coming to Southeast L.A. and the Gateway Cities,” Hahn stressed. “This region has been left behind on so many levels… while other places in L.A. County get those shiny new trains… We will finally make good on the promise we made to Southeast L.A. that you too will have a fantastic public transportation system.”

Metro’s Southeast Gateway Line is planned to run 19 miles, from the city of Artesia to downtown Los Angeles Union Station.

Metro map of planned Southeast Gateway light rail line

When construction costs rose, Metro approved building the lower end of the line first, saving the connection to downtown L.A. for later. The initial segment will extend from Artesia to the South L.A. community of Florence, with connections to the Metro A and C Lines. That initial 14.5-mile phase is expected to cost $7.1 billion.

The line’s final environmental studies were approved this past April. In August, the Federal Transit Administration made the project eligible for significant – and much needed – federal funding. The project already has about $3.5 billion in funding (mainly Metro sales tax revenue) and was awarded a $261 million CA transit capital grant last week. But a sizable gap remains.

State Senator Bob Archuleta (left, in blue jacket) and State Assemblymember Blanca Pacheco (center, in white jacket) present a giant check yesterday – representing the recent $261 million California State Transportation Agency Transit and Intercity Rail Capital Program grant

“I understand very clearly that this project will not get built without significant federal support,” U.S. Representative Robert Garcia emphasized. He then pledged, “We’re going to get that money. We’re going to get past this election – regardless of the outcome – and fight like hell to get every single dollar that this project deserves.”

Representative Robert Garcia underscored the importance of securing federal funding for the Southeast Gateway Line

Metro CEO Stephanie Wiggins noted the importance of utility relocation in reducing delays and containing costs, and also pledged to work with Representative Garcia to secure federal funds. Wiggins expressed her appreciation for the partner cities, agencies, utilities, and Metro staff that spent decades getting the Southeast Gateway Line, “the most deserving project, the biggest priority we have at Metro,” to where it is today.

Metro CEO Stephanie Wiggins speaking on the future Southeast Gateway Line
Much of the Southeast Gateway Line will be located in the former West Santa Ana Branch rail right-of-way

Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.

More from Streetsblog Los Angeles

Friday Bike Updates: New 2nd Street Bike Lane, and Two Upcoming CicLAvias

April 24, 2026

The Week in Short Video: Sponsor Streetsblog L.A.’s Great Commuter Race!

April 24, 2026

Opposition Melts Away as Durazo Announces Major Changes to SB 1361

April 24, 2026

Friday’s Headlines

April 24, 2026

Eyes on the Street: South El Monte’s Safe Routes to School Improvements

April 23, 2026
See all posts