Metro Committee OKs Moving Forward with DTLA L.A. River Path Environmental Studies

Path types under consideration for Metro’s L.A. River path

Note: Metropolitan Shuttle, a leader in bus shuttle rentals, regularly sponsors coverage on Streetsblog San Francisco and Streetsblog Los Angeles. Unless noted in the story, Metropolitan Shuttle is not consulted for the content or editorial direction of the sponsored content.

This afternoon, the Metro board Planning and Programming Committee approved proceeding with the next steps on the L.A. River bike/walk path through central Los Angeles. The committee approved receiving the project's conceptual design report and initiating the Draft Environmental Impact Report (DEIR) process. The action is subject to full board approval next week.

This river path project will be located in the cities of Los Angeles and Vernon. It will serve communities including Boyle Heights, Lincoln Heights, Chinatown, and downtown L.A. The project is a roughly 8-mile gap closure that will create a 30+mile continuous bikeway from Griffith Park to Long Beach.

The central L.A. River path has $365 million in Measure M funding. Measure M specifies a completion date in fiscal year 2025-2027.

Metro has hosted several rounds of public input meetings for the project.

The conceptual design report (executive summary) includes three alternatives.

L.A. River path alternative A
L.A. River path alternative A
L.A. River path alternative A
L.A. River path alternative B
L.A. River path alternative B
L.A. River path alternative B
L.A. River path alternative B
L.A. River path alternative B
L.A. River path alternative B

The alternatives have plenty in common. They all include entrances on both east and west sides, with about half of the entrances on each side. They all include 6-7 new bike/ped bridge crossings.

Unfortunately, they are all expensive - likely to require more money than the $365 million in hand. Elevated sections tend to drive up the cost; channel-top sections tend to be somewhat less expensive. Metro's current rough cost estimates are:

    • Alternative A - $329-$443M - 48% channel top, 15% elevated
    • Alternative B - $393-$523M - 23% channel top, 31% elevated
    • Alternative C - $332-$446M - 26% channel top, 33% elevated

More expensive elevated sections are positive for year-round access, though they also mean hills/grades and can mean structures that block views and potential future access to a revitalized river down the line.

At today's committee meeting, public comment was strongly in favor of the project. Commenters included representatives of the Anahuak Youth Sports Association, L.A. County Bicycle Coalition, ActiveSGV, and Climate Resolve. Several advocates urged Metro to focus on alternatives that would remain open during rain events.

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

New UCLA Report Looks into the High Cost to Build Parking

For new apartments, the research found that building required parking adds roughly $50,000 to $100,000 per unit, and disproportionately increases the cost to build smaller apartments

March 2, 2026

This Week In Livable Streets

Metro NoHo-Pasadena BRT meetings, Westwood Blvd. safety project, Chandler bikeway extension, Metro PSAC, and more

March 2, 2026

Monday’s Headlines

ICE, CicLAvia, Ride that D, large asphalt repair, Long Beach, car insurance, AQMD, Pasadena, Glendale, Wilmington, Black history, car-nage, and more

March 2, 2026

“Disrespectful” and “infuriating”: L.A.’s progress on making streets safe and accessible for disabled people stalled for decades

Curb ramps have been required when repaving a street since 1992. Why is L.A. only now saying it must follow the law?

February 27, 2026

Friday’s Headlines

Metro D Line, Wilmington ped/bike bridge, parking, Carson, Pasadena, oil, WeHo, Downey, car-nage and more

February 27, 2026

SGV Bus Rapid Transit Gets Another $3.9M for Study and Design

Early improvements combine for about 14 miles of continuous bus lanes, expected to be installed in advance of the 2028 Olympic games

February 26, 2026
See all posts