Audit Finds U.S. DOT’s Transit Record-Keeping ‘Unreliable,’ ‘Inaccurate’

The disjointed state of "New Starts," the Federal Transit Administration's (FTA) program to fund new rail and bus lines, is well-known
on the Hill -- in fact, House transportation committee chairman Jim
Oberstar (D-MN) recently quipped that it ought to be renamed "small
starts, low starts, and no starts."

With
Oberstar's six-year transportation re-write bill in limbo for the
moment, however, there appears to be scant political urgency to fix the
program. But a report released today by the non-partisan Government
Accountability Office (GAO) could help change that picture.

It can take as long as 14 years for transit planners to secure a
full-funding New Starts grant agreement (FFGA), the final stage
required before starting construction. Yet when GAO auditors set out to
break the process down by its stages (which are depicted in a comically
complex chart after the jump) they found the FTA could only provide
complete information for 9 out of 40 New Starts projects approved since
1997.

"We were unable to obtain complete and reliable
project milestone data from FTA," GAO auditors wrote. An attempt to
confirm records for a random sample of 10 New Starts projects found the
information to be "unreliable and, in some cases, inaccurate."

The GAO report then outlined the FTA's explanation for its inconsistent data:

First,FTA told us that it does not have records on when a project beginsalternatives analysis because this phase is conducted at the locallevel, generally without FTA involvement. Second, FTA told us that itdoes not record when a project sponsor submits an application forpreliminary engineering, final design, and FFGA because projectsponsors almost never submit complete applications.

The
bureaucratic hurdles that transit planners must clear to win federal
aid stand in stark contrast to road projects' usually unobstructed path
to approval. But without solid data to make the case for fixing New
Starts, transit advocates' already arduous political fight for fairer
treatment is likely to get even harder.

The GAO report can be downloaded in full here.

d09784_0009.jpg

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

Wednesday’s Headlines

In addition to Southern California hillsides ablaze, today's headlines also touch on sidewalks, bus shelters, the 710 and 14 Freeways, Pasadena, Big Blue Bus, high-speed rail, and more

September 11, 2024

Metro and Caltrans 14 Freeway Expansion Project Meetings Delayed

Metro plans to add more general purpose lanes as part of its 14 Freeway expansion project through Santa Clarita - a part of L.A. County that is reeling from triple digit heat

September 10, 2024

Tuesday’s Headlines

Scorching climate-catastrophe-driven heat continues, plus broken sidewalks, 710 Freeway homes, 14 Freeway expansion, carnage, a Santa Monica woonerf, and more

September 10, 2024

This Week In Livable Streets

CicLAvia in Lincoln Heights, Burbank council candidates forum, Glendale greenway, Metrolink, Highway 14 expansion, Noche de las Luminarias, Metro Youth Council, and more

September 9, 2024

Wider Won’t Work: Wider Highways Are a Prescription for an Unhealthy Future

Metro/Caltrans highway expansion will encourage more vehicle trips, exposing already disadvantaged, environmental justice communities to even more pollution, with lifelong health impacts

September 9, 2024
See all posts