Audit Finds U.S. DOT’s Transit Record-Keeping ‘Unreliable,’ ‘Inaccurate’

The disjointed state of "New Starts," the Federal Transit Administration's (FTA) program to fund new rail and bus lines, is well-known
on the Hill -- in fact, House transportation committee chairman Jim
Oberstar (D-MN) recently quipped that it ought to be renamed "small
starts, low starts, and no starts."

With
Oberstar's six-year transportation re-write bill in limbo for the
moment, however, there appears to be scant political urgency to fix the
program. But a report released today by the non-partisan Government
Accountability Office (GAO) could help change that picture.

It can take as long as 14 years for transit planners to secure a
full-funding New Starts grant agreement (FFGA), the final stage
required before starting construction. Yet when GAO auditors set out to
break the process down by its stages (which are depicted in a comically
complex chart after the jump) they found the FTA could only provide
complete information for 9 out of 40 New Starts projects approved since
1997.

"We were unable to obtain complete and reliable
project milestone data from FTA," GAO auditors wrote. An attempt to
confirm records for a random sample of 10 New Starts projects found the
information to be "unreliable and, in some cases, inaccurate."

The GAO report then outlined the FTA's explanation for its inconsistent data:

First,FTA told us that it does not have records on when a project beginsalternatives analysis because this phase is conducted at the locallevel, generally without FTA involvement. Second, FTA told us that itdoes not record when a project sponsor submits an application forpreliminary engineering, final design, and FFGA because projectsponsors almost never submit complete applications.

The
bureaucratic hurdles that transit planners must clear to win federal
aid stand in stark contrast to road projects' usually unobstructed path
to approval. But without solid data to make the case for fixing New
Starts, transit advocates' already arduous political fight for fairer
treatment is likely to get even harder.

The GAO report can be downloaded in full here.

d09784_0009.jpg

Stay in touch

Sign up for our free newsletter

More from Streetsblog Los Angeles

Eyes on the Street: Traffic Calming Rain Gardens Nearly Completed in Glendale

Sweet new sidewalk rain gardens are components of Glendale's 1.5-mile-long La Crescenta Avenue Rehabilitation Project. Also coming soon: bike lanes, decorative crosswalks, and more.

December 12, 2025

Friday’s Headlines

ICE, large asphalt repair, Camino City Terrace, bikes on buses, LAPD, Beverly Hills, Glendale, Pasadena, Santa Monica, WeHo, and more

December 12, 2025

City of Industry Working Towards 10-mile Bike Path

The project will begin where it’s needed most – Valley Boulevard.

December 11, 2025

Thursday’s Headlines

ICE, resurfacing scandal, YIMBY lawsuit, DIY crosswalks, ped safety, open streets, SGV greenways, LAPD, car-nage, and more

December 11, 2025

Eyes on the Street: G Line Busway Bridge Over Van Nuys Blvd

Metro G Line upgrades are expected to be complete in 2027

December 10, 2025
See all posts