DC’s Silver Line: A Transit Expansion 34 Years in the Making

When a politician like Maryland Governor Larry Hogan kills off a transit project, not only does he rob citizens of anticipated improvements, he could be wiping out decades of intricate planning.
Dan Malouff at Greater Greater Washington notes that by 2019 it will have taken 34 years to complete the Metro’s Silver Line, which will connect DC and suburban counties with Dulles Airport.
Malouff explains the above graphic:
The timeline begins in 1985, when the idea of a Metro line to Dulles Airport went from vague concept to serious planning initiative following a study that determined it would be feasible.
Planning (yellow on the timeline) and environmental work (green) took the next 21 years, until 2006. It took another 3 years for officials to finalize funding (blue) before construction (purple) could begin in 2009.
Plopping a rail line down the middle of a gargantuan suburban highway with a capacious median is easy compared to putting one virtually anywhere else. Almost any other potential Metrorail expansion imaginable will be harder to plan, fund, and build.
“That doesn’t mean it’s not worth doing,” Malouff writes. “But it’s definitely going to be hard.”
Elsewhere on the Network today: Streets.mn tests whether motorists are yielding to pedestrians; and Biking Toronto reports that there is fresh green paint, but no physical separation, on a much-needed bike lane.
Read More:
Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.