SGV Celebrates New Fullerton Road Rail Grade Separation

After ten years of grade separation work, the road will reopen to drivers in a matter of days, with a dedication to former Congressmember Grace Napolitano.
12:23 PM PDT on October 29, 2026
SGV Celebrates New Fullerton Road Rail Grade Separation
The ribbon cutting for the grand opening of the Fullerton Road Grade Separation. All photos by Chris Greenspon/SBLA

The San Gabriel Council of Governments held a ribbon cutting and dedication ceremony for the Fullerton Road Grade Separation in City of Industry on Wednesday. The long closed-for-construction Fullerton Road will reopen in a few days.

Just as SGVCOG president and Claremont vice mayor Ed Reece began the program, a freight train went by overhead, delighting the audience as Reece gestured upward.

SGVCOG President Ed Reece begins the ceremony for the reopening of Fullerton Road.

After a minute or two of train noise mixed with laughter, Reece jumped back into his speech, rattling off statistics and facts about the decade-long project.

The central area marked in fuchsia is the location of the project.

The Fullerton Road Grade Separation features a six-lane roadway underpass, and three bridges above: a four-track railway, a vehicular bridge for Railroad Street, and a pedestrian bridge. About 90 trains pass through per day, while 25,000 cars are expected to drive under them.

The pedestrian bridge was built from 2.5 million pounds of steel. The rail and vehicular bridges were poured with 19,000 cubic yards of concrete. The underpass required 62,000 cubic yards of dirt to be excavated. This is the 17th of 19 grade separations for the Alameda Corridor East, and it cost nearly $275 million. 

“This roadway underpass and the impressive structure towering above us stands as a powerful testament to our collective resolve to elevate safety and mobility within the City of Industry, Rowland Heights community, and the larger San Gabriel Valley,” Reece said. 

The Rowland Raiders high school marching band tunes up for the ceremony.
Construction workers admire their work.
SBLA reporter Chris Greenspon takes in Fullerton Road’s new pedestrian bridge.

For the project’s entire duration, the nerves of locals have been tested. Fullerton previously functioned not just as an arterial road to Orange County, but also a relief valve for the Puente Hills. For ten years, drivers detoured to Nogales Street or Azusa Avenue, and getting past Fullerton on Gale Avenue during rush hour meant waiting through numerous traffic light rotations. Drivers passing by honked their horns in relief that it would all soon be over.

City of Industry Mayor Cory Moss recounted the trials and tribulations of the work.

“The original contractor abandoned the project, citing design issues. There were significant delays going through the process of awarding the project to a new contractor. We had utility relocation complications and coordinating challenges with various partners that added even more hurdles,” Moss said, adding that “it seemed like every time we thought there cannot possibly be something else that would go wrong that would further delay this project, I felt like this project said, ‘Hey, dude, hold my beer.’”

Now that it’s finished, the road will be open again in a matter of days. Presumably, crews are installing a final handrail on the stairway to the pedestrian bridge.

Construction workers put finishing touches on the Fullerton Road Grade Separation Project.

The entire project was dedicated to retired Congressmember Grace Napolitano. After thanking the project’s construction workers, La Verne Mayor Tim Hepburn detailed her many achievements.

Napolitano began her political career on Norwalk City Council in the 1980s, moving on to State Assembly and U.S. Congress in the 1990s, serving thirteen terms there until 2025. Mayor Hepburn touted her work on the Transportation and Infrastructure Committee, where she advocated for the Metro A Line extension, secured federal funding for improved bus service in the region, and brought the bottleneck at the SR 57-60 confluence to the attention of U.S. Secretary of Transportation Anthony Fox.

“She’s the only member of Congress that I can recall who, right in the middle of one of our meetings, picked up the phone and called the CEO of Union Pacific Railroad to ask that the company come to the table and immediately address our concerns,” Hepburn said about the Grade Separation project. “She didn’t just take notes. She didn’t just promise to follow up. She picked up the phone and got to work. And that, ladies and gentlemen, is what I call fierce advocacy.” 

Hepburn finished, “Grace, this project stands as a permanent reminder of what your leadership helped make possible, and of the lasting difference one dedicated public servant can make in the lives of so many. Thank you.” 

The plaque dedicating the project to Former Congressmember Grace Napolitano is unveiled.

Streetsblog’s San Gabriel Valley coverage is supported by Foothill Transit, offering car-free travel throughout the San Gabriel Valley with connections to the A Line Stations across the Foothills and Commuter Express lines traveling into the heart of downtown L.A. To plan your trip, visit Foothill Transit. “Foothill Transit. Going Good Places.”Sign-up for our SGV Connect Newsletter, coming to your inbox on Fridays!

Photo of Chris Greenspon
Chris Greenspon is the San Gabriel Valley Reporter for Streetsblog L.A. and co-host for SGV Connect.

Read More:

Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.

More from Streetsblog Los Angeles

Five Simple Hacks to Avoid L.A. City Speed Camera Tickets

October 29, 2026

Thursday’s Headlines

October 29, 2026

Wednesday’s Headlines

October 28, 2026

Tuesday’s Headlines

October 27, 2026

Redondo Beach Installs Curb-Protected Bike Lanes on Palos Verdes Blvd.

October 26, 2026
See all posts