Caltrans
Streetsblog LA
Caltrans Planning Three Complete Streets Projects in L.A. County
Caltrans is planning nearly $5 million worth of L.A. County complete streets improvements - on Pacific Coast Highway, Santa Monica Boulevard, Alvarado Street, Glendale Boulevard, and Western Avenue
September 22, 2021
Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags
Construction started on SR-71 segment 1 less than two months ago and is already 3-6 months behind schedule. Segment 2, budgeted to cost $40 million now faces a $61M construction funding shortfall.
September 10, 2021
Metro Completes Design for 210 Freeway Crash Barrier to Keep Trucks Off Gold Line
The six-mile 210 Freeway barrier through Pasadena and Arcadia costs $425M. If funded, it could be completed in 2028.
September 9, 2021
Paused 710 Freeway Widening Project is the Focus of Two New Committees
The fate of the 710 is being discussed at the Gateway Cities Council of Governments I-710 Ad Hoc Committee, and will soon be discussed at Metro's new I-710 South Corridor Task Force.
August 31, 2021
Caltrans SGV District Collecting Public Comments for Active Transportation Plan
Caltrans is seeking public input in developing its local Active Transportation Plans. The L.A.-Ventura plan will identify locations for bicycle and pedestrian improvements on, across, or parallel to the state highway system.
July 30, 2021
Metro Moves to Revive Canceled High Desert Freeway Project
It appeared that cancellation of Metro's High Desert Corridor Freeway meant that voter approved "mutli-purpose" funding would go to rail. Now Metro Highways are moving to steer the money widen another highway nearby.
July 30, 2021
Pomona Families Holding Out Against Caltrans/Metro Home Demolitions for 71 Widening
To widen the 71, Caltrans has already demolished 15 Westmont homes, with 3 additional homes still threatened - in addition to the 6 homes the agency demolished a decade to make way for the Mission Boulevard Bridge.
July 13, 2021
Gateway Council of Governments to Host Freeways Meeting on July 7
Interested readers should make plans to attend the GCCOG Zoom meeting on Wednesday July 7 starting at 6 p.m.
July 2, 2021
Caltrans and Metro Break Ground On 71 Freeway Widening Through Pomona
The SR-71 project will convert about 3.5 miles of existing four-lane expressway into an eight-lane freeway. Construction for the first phase - $174 million for just under two miles - is expected to complete in 2024.
June 17, 2021
Local Caltrans Director Tavares Disputes Metro Highway Chief Ansari Account of 710 Pause
Tavares on pausing 710 Freeway widening: "I don't know where Mr. Ansari came up with that comment. I've had numerous conversations and discussions and meetings... regarding that corridor."
June 10, 2021