Report: Expo Phase II Will Open in 2015

The future home of Bergamont Station in Santa Monica.  Photo: Darrell Clarke/Friends for Expo
The future home of Bergamont Station in Santa Monica. Photo: ##http://www.friends4expo.org/expow.htm##Darrell Clarke/Friends for Expo##

Expo supporter Gökhan Esirgen attended a special meeting of the Westside Neighborhood Council last night featuring a presentation by the Expo Construction Authority.  Esrigen sent an email afterwards to other supporters and media, which can be read after the jump, but here are some of the highlights of Expo’s presentation.

  • Expo believes they can open the line all the way to 4th and Colorado by “early 2015”
  • Two teams are bidding on construction.  The winning bid will be announced at the February 2011 Board Meeting
  • The Bike Path is a separate contract but construction will be coordinated with the light rail construction
  • There’s still a lot of details to be worked out at crossings and involving parking

Given some of the delays that have plagued construction of Phase I, it’s hardly a sure bet that Phase II will be running smoothly five years from now.  Still, for those Westsiders hungry for their first rail line, the end is in sight.  Conversely, those hoping to block construction until the line can be built below-grade have a ticking clock to contend with.

Yes, guys, you heard it right. There was a lot of discussion around, some mentioning of memos by Metro pointing to opening dates in 2016 or even 2017. But tonight, at the WNC meeting, Expo officially announced that they are aiming for an early-2015 Phase 2 revenue-operations start to 4th and Colorado in Santa Monica.

The bids by the two competing teams will be announced at the December Expo board meeting. The winning team will be announced at the February 2011 board meeting. Notice to proceed will be issued in March and that’s when the final design and utility relocation will start.

It was said that the main risk for delay for the project would be third parties, such as the City or utility companies, not timely assigning permits or doing the necessary work.

Venice bridge will be a separate contract, not part of the contract that will be made with one of the two competing teams. It’s a possibility that Balfour Beatty Infrastructure, Inc, who are building the bridge east of Venice, will also build the bridge west of Venice. The construction of this bridge could start in a few months.

The bike and pedestrian path will also be a separate contract as well but it will be jointly coordinated with the LRT contract.

There was a lot of detailed discussion of the grade crossings, how much delay there will be, how the lights will be synchronized, how the queue cutters will work, etc. (The queue cutter at Overland is electromagnetic loops in the ground detecting cars and connected to a traffic signal at the pedestrian crossing north of the tracks, cutting the queue so that the cars don’t back up to the tracks).

Under the no-parking option, the tracks will be shifted to the south side of the 200-ft-wide right-of-way between Overland and Westwood and the 100-ft-wide area north of the tracks will be left as vacant land for whoever wants to build a park there in the future.

Because of the new relocation of the tracks (such as in the no-parking option), the contractor will restudy the sound impacts when they’re doing the final design.

Partial opening of Phase 2 (such as to Palms) is not a possibility. Testing was said to be very expensive and not worth for a mile-long segment. In addition the EIR didn’t study phased openings. Last but not least, there are concerns that partial openings will delay the final opening to Santa Monica.

Virtually no one showed up from NFSR, certainly none of their leaders. Apparently their lawyers advised them not to interact with the Expo Authority.

ALSO ON STREETSBLOG

Expo Phase II Construction Updates

|
Join us for an update on Expo Phase 2! The Exposition Construction Authority invites you to a construction update community meeting for Phase 2 of the Expo Line project. Stakeholders will receive information on upcoming construction activities and timelines. The format will include a short presentation followed by an Open House session to facilitate dialogue and community input.Los Angeles […]

Expo Phase 2 Update Meetings

|
The Exposition Construction Authority invites you to a construction update community meeting for Phase 2 of the Expo Line project. Stakeholders will receive information on upcoming construction activities and timelines. The format will include a short presentation followed by an Open House session to facilitate dialogue and community input. Santa Monica Construction Update Tuesday, January 21, 2014 6:30 […]

Expo Phase II Community Meetings

|
The Exposition Construction Authority invites you to a construction and design update community meeting for Phase 2 of the Expo Line project. Stakeholders will receive information on upcoming construction activities and design progress. Progress renderings will be available at the meeting. The format will include a short presentation followed by an Open House session to facilitate dialogue […]

Community Meetings for Design Updates on Expo Phase 2

|
The Exposition Construction Authority invites you to a design update community meeting for Phase 2 of the Expo Line project. Stakeholders will receive information on design progress and will have the opportunity to view progress renderings. The format will include a short presentation followed by an Open House session to facilitate dialogue and community input. […]

It’s Official: Expo Construction Contract, Aerial Station, and No Westwood Parking Approved by Expo Board

|
Earlier this afternoon, the Expo Construction Authority Board of Directors approved a $541.7 million design-build contract to the Skanska/Rados team, a no-commuter parking option for the Westwood Station and an aerial station for the Sepulveda Boulevard Station.  Earlier in the day, the Los Angeles City Council had unanimously backed the Rosendahl/Koretz motion funding the Sepulveda […]